Article 250

Grounding and Bonding

250

Grounding and Bonding

Wiring and ProtectionNEC 2008NEC 2020NEC 2026

Summary

System grounding, equipment grounding, bonding of services and separately derived systems, GECs, EGCs, and electrode systems.

Tables 250.66 and 250.122 and electrode rules (250.52/250.53) are core exam material.

  • Grounding = system reference; bonding = intentional metallic path continuity.
  • GEC size often from Table 250.66; EGC from 250.122.
  • Main bonding jumper and supply-side bonding jumper are distinct.

Study notes from the app's code library — always confirm with the official NEC book your AHJ adopts.

Sections in Code Lookup (94)

Practice questions (39)

  1. 1.The general requirements for grounding and bonding of electrical systems are found in Article 250.

  2. 2.Grounded systems are generally required to be grounded as provided in 250.20.

  3. 3.An unspliced main bonding jumper is required to connect the equipment grounding conductor(s) and the service-disconnect enclosure to the grounded conductor within / at each service disconnect, where the system is grounded, as stated in 250.24 / 250.28.

  4. 4.Metal underground water pipe in contact with the earth for 10 ft or more is a recognized grounding electrode in 250.52.

  5. 5.A ground ring consisting of at least 20 ft of bare copper not smaller than 2 AWG encircling the building/structure is a recognized electrode.